Typical Installation Sequence
To minimise the on-site erection time,
ParkUp modules arrive pre-assembled
complete with parapet assemblies and under deck lighting.
Subject to clear access to the assembly area a 100 space
parking deck can be completed in just 5 days.
A typical installation sequence for a 100 space deck is
as follows:
|

|
Day 1
- Establish Site, isolate from the public and ensure all safety measures are in place
- Set out the column positions and install edge decks and parapets, line and level in preparation for the installation of the intermediate decks
- Continue with the installation of the intermediate decks
- Install the braced bays as required
- Install the first staircase
|

|
Day 2
- Continue with the installation of intermediate deck units and parapets
- Complete the lighting under the installed section
- Install braced bays as required
|

|
Day 3
- Continue with the installation of intermediate deck units and parapets
- Complete the lighting under the installed section
- Install braced bays as required
- Possible partial handover of under deck area for parking
|

|
Day 4
- Continue with the installation of intermediate deck units and parapets
- Complete the lighting under the installed section
- Install braced bays as required
|

|
Day 5
- Complete the installation of the intermediate deck units
- Install the edge deck units and parapets
- Install the ramp unit and supports
- Install the second staircase
- Finish off lighting connections and upper deck lighting
- Clear site
|
|
|
|
|
|