Typical Installation Sequence

To minimise the on-site erection time, ParkUp modules arrive pre-assembled complete with parapet assemblies and under deck lighting.

Subject to clear access to the assembly area a 100 space parking deck can be completed in just 5 days.

A typical installation sequence for a 100 space deck is as follows:





Day 1

  • Establish Site, isolate from the public and ensure all safety measures are in place
  • Set out the column positions and install edge decks and parapets, line and level in preparation for the installation of the intermediate decks
  • Continue with the installation of the intermediate decks
  • Install the braced bays as required
  • Install the first staircase



Day 2

  • Continue with the installation of intermediate deck units and parapets
  • Complete the lighting under the installed section
  • Install braced bays as required



Day 3

  • Continue with the installation of intermediate deck units and parapets
  • Complete the lighting under the installed section
  • Install braced bays as required
  • Possible partial handover of under deck area for parking



Day 4

  • Continue with the installation of intermediate deck units and parapets
  • Complete the lighting under the installed section
  • Install braced bays as required



Day 5

  • Complete the installation of the intermediate deck units
  • Install the edge deck units and parapets
  • Install the ramp unit and supports
  • Install the second staircase
  • Finish off lighting connections and upper deck lighting
  • Clear site

tel: +44 (0) 1291 623 801 | fax: +44 (0) 1291 625 453
email: mail@mabeybridge.co.uk

Copyright © Mabey Bridge Ltd 2009
tel: +44 (0) 1291 623 801  |  fax: +44 (0) 1291 625 453
Copyright © Mabey Bridge Ltd 2009